Construction Diary Overview of the four stages of construction Week one September 19 2004 - vegetation clearance Week two September 26 2004 - digging begins Week three October 3 2004 - relocating reeds and wildlife Week four October 10 2004 - profiles start to take shape Week five October 17 2004 - sluice construction begins Week six October 24 2004 - linking the reed bed to the existing water meadows Week seven October 31 2004 - connecting to the Winterbourne and replacing top soil Week eight November 7 2004 - the viewing mound is formed Week nine November 14 2004 - images of the double vortex Week ten November 21 2004 - the earthworks are nearing completion Week eleven November 28 2004 - the contractors move off site until Spring Spring action May 10 2005 - work recommences in preparation for the public launch on June 25 |
||